PROJECT DETAILS

ADDRESS:

96-166 Centre Rd, Narre Warren VIC 3805


DEVELOPER:

Osanrae


ARCHITECT:

Demaine


No. of dwellings:

97 Townhouses


Builder

Demaine


Set among a spectacular natural environment dotted with wetlands, native woodlands and gentle bodies of water, Casey Green invites you to experience modern community living at its best. Located just moments from one of the city’s key recreational pedestrian and cycle paths, the Hallam Valley Trail, and only 2km from the shops, services and eateries of Narre Warren town centre, settle back in peaceful, stunningly landscaped streets lined with beautiful maples and elms, and discover an idyllic residential oasis, brilliantly located close to everything you need.

Tucked among sheltered, tree-lined avenues, these outstanding single and double-storey homes offer a selection of three bedroom layouts in an attractive array of facade styles. Well-designed and highly liveable, Casey Green homes present outstanding value and exceptional quality. Choose from a vibrant palette, multiple styles, and a suite of optional extras. Designs like Clover, Fennel, Gum, Lily, Oak and Wattle deliver a comprehensive range to suit your taste and lifestyle requirements – and sit side by side in a streetscape that is both visually diverse and filled with character.

Project Update

  • Expected Construction Completion: End 2020/Early 2021
  • Expected Settlement: End 2020/Early 2021
  • Contact: [email protected]

Stage 6 Project Update - September 2020

The following works have taken place on site since the last update:
  • Timber framing works 90% complete
  • Structural steel works 100% complete
  • External cladding works 80% complete
  • Windows and roof tile works 90% complete
  • Plastering works 80% complete
  • Internal fitout and finishing works commenced
  • Driveways and external fencing works 80% complete
  • Landscape works commenced

Works planned on site for the next quarter of 2020:
  • Completing all remaining internal and external works
  • Performing final cleans and defect inspections
  • Preparing for settlement and handover

Anticipated settlement:
Lots 106 to 116 – End 2020
Lots 117 to 127 – End 2020
Lots 241 to 245 – End 2020
Lots 139 to 150 – Early 2021

We will continue to update quarterly. In the meantime, if you have any queries regarding the development please contact [email protected].